Skip to main content

first bug of #Project2013 #sp1

Interesting - Setting Baseline0  adds values to ALL baselines.  Then editing Baseline0 costs changes all baseline costs

Repro:

  • Create task of 1d
  • Add a cost resource
  • Set Task Usage at bottom window
  • Add Baseline 0 Cost, Baseline 10 cost, baseline 4 cost (or some others too)
  • Add some Timephased costs into Cost timephased field
  • Set baseline
  • All baselines are set with a value
  • Edit Baseline0 Cost TImephased entry
  • All Baseline Values change
  • Scream and bang head on table
** UPDATE **

Having looked further into this it appears that this only impacts baseline cost timephased values.  However this is a MASSIVE impact as it could increase file sizes fairly significantly as the Baseline Cost Timephased Values for Baselines >=1 are no longer independent values.  Put simply, BAseline 1-10 Cost Timephased will equal Baseline0Cost, and cannot be set independently.

Here is an updated repro

Prep:
- Firstly create split view with task usage on the bottom and gantt at the top
- add Cost, baseline Cost, Baseline1 cost, other baseline cost fields to the Task Usage Timephased section
Repro:
1) Create a task (any duration)
2) assign a resource to the task that has a standard rate so we see costs timephased in task usage pane
3) Now set Baseline0
BUG:  See that Baseline 1-10 Cost values in timephased data now all have a value, not just the baseline0cost value
4) Now edit an element of the timephased baseline0 cost data
BUG:  All Baseline Cost Values change in that time segment to the value you edited
5) Now try edit a timephased segement for basline 1 cost
BUG:  Notice the edit wont set
6) now try settings Baseline 1 (or another >0)
BUG:  Timephased BaselineX Cost Values NOT Created


here's what a plan can look like when baseline0 is set.  In the bottom pane I have added Basline0 Cost, Baseline1 Cost and Baseline10 Cost but the same issue applies for all of them.





Note;  baseline work values do not show this issue

Comments

Popular posts from this blog

#projectserver2013 VIEW FAILURE: The view failed to load. Press OK to reload this view with the default settings. Press cancel to select another view.

** UPDATE ** includes notes relating to secondary bug where Timesheet is created without Administrative tasks.

Does this ring any bells?

This has been bugging me for months, but finally I have a repro for this:

Issue Summary:  When a task is deleted from a plan that is approved into a previous or current timesheet - even when there are no actuals on the task - you can no longer view the timesheet

The following repro has been proven:
- Setup system with Single Entry Mode, with enforced Status Approval before Timesheet Approval
- Create resource as own timesheet manager
- Create new project
- Create two tasks in the same week, starting monday with 5 days duration:  1) Task to assign actuals, 2) Task to delete post submission
- Assign Resource to tasks
- publish project
- as Timesheet User, go to the appropriate timesheet period for the tasks created
- Assign actual work to one task (task 1), leaving task 2 with no actual work
- Submit timesheet
- as Project Status Manager, approve the time on task 1 …

What to do when your application server goes bang

What happens when someone kills your Application Server?
So imagine the scenario:
Three Server Solution - SQL - SharePoint 2010 and Project Server 2010 Application Server (Central Admin Host) - Wfe/ReportServer
We wake one bleary Monday morning to find that some numpty has killed the application server and the users are baying for blood.
Well surprisingly SharePoint handles this disaster recovery scenario particularly well.  Well.  Better than I thought it would to be honest.
Rough steps:
- quick SQL backup to be safe - Rebuild your application server - reinstall pre-reqs - reinstall SP, PS, SPFSP1, SPS+PSSP1, Cumulative Update and other stuff you usually put on there. - Run your configuration wizard to reattach to the Farm, and select Host CA Site
The last step was what I was VERY wary of.  Would the server simply reattach to the Farm, even when there is no CA server available?  
Bingo your back.... almost.... you are going to get errors a-gogo in your event log as things just aren't quite back…

Reporting from Project Server 2016 - multiple sites and userviews

Just a quickie...
I've been interested in how MS have handled the "multiple PWA sites in a Content DB" thing since I read that this was their new approach.  Most of my reporting is via SSRS so i am reliant (still... in 2016) on DB queries rather than OData feeds (tsk) and this "querying a PWA DB with more than one PWA site in it is unsupported" quote was worrying me.

So it looks like what is happening is this.

When you create the first PWA site in a Content DB it hard-codes the SiteID into the _Userview view design elements.  This means that your first PWA Site is the default.  All the data for subsequent sites are still held in the tables against separate SiteID's but you cannot utilise the OOTB _Userview components (see below)


SELECT        ProjectFields....
FROM            pjrep.MSP_TVF_EpmProject('FF19B767-CA6D-4C4C-B123-C0B5AE5354D6') AS MSP_EpmProject 
LEFT OUTER JOIN
                      pjrep.MSP_TVF_EpmInternalProjectHierarchies('FF19B767-CA6…