Skip to main content

Using the RESUME field to reschedule incomplete work #projectserver

Since MS provided the ability to plan only using PWA, this has been a really useful feature for some users.  However there has always been a (certainly from my perspective) perceived issue, in that the ability to reschedule incomplete work into the future (a key component of the planning cycle) was only available in MS Project client.

The other day I was asked by a customer how they could get around this issue.  They use PWA extensively (cost reasons) for planning but were struggling with realising correct resource forecast data as they PM's were not able to re-forecast their remaining work schedule.

As we had recently patched the Project Server to 2013 SP1 + 0614CU I thought I would look at the STOP/RESUME fields in the Project views to see if these were editable, and surprise surprise they were.

The stop/resume fields are how MS Project handles task splits and the "update remaining work to restart after" component of rescheduling.  The Stop field will indicate the last day that progress was added to the task (either via % Complete or Timephased Actual Work edits/status updates) and by default the resume field will be the next day (or minute, in truth)

If you edit the resume field to a date in the future, then the task becomes split and the remaining work moves forward to restart from that date.

Don't ask me to explain multiple or manual splits.  I can't

Anyhoo... the repro

Firstly create a new project, with one task on it with 10d duration for simplicity of querying, and assign one resource to the assignment and publish the schedule


As the user assigned to the task, complete the first day of actual work and submit

As the Project Owner, approve the task.  Then go into Approval History and publish the assignment

Wait until it publishes

Then open the project in PWA for editing.

Set the Resume date to some time in the future, in this example 18th August
Note the finish date changes

Now query the assignmentbyday table and see the work move forward (ignore the nulls in my results, these have been replaced in my query to make it easier to discern between 0's and 8's!)


Notice that the planned work now has a gap between the 1d actuals assigned and the Resume date of 18 August

HURRAH!!!




Comments

Popular posts from this blog

Restoring PWA Site to another Web App in the same Farm

The scenario is this: SharePoint 2016 Farm with Project Server Two Web Apps Development UAT One PWA on Development Web App. I want to copy the PWA Site on Development web app to UAT to support a testing cycle. As far as I knew there were two options: 1) Content Database Restore and Attach Process would be backup your Dev Content Database, Restore to a new Content Database for QA, then mount the database on the appropriate web app and your off.... Problem:  Although you can do this with the -AssignNewDatabaseID switch in Powershell (to avoid two content db's having the same database id) the Site Collection (PWA) in the db still retains its SiteID which means there is a duplicate SiteID in the Configuration Database.  This stops the PWA site being created and alllocated correctly and becomes essentially orphaned. This method is only any good for MOVING not COPYING Back to the drawing board... 2) Backup-SPSite / Restore-SPSite I didn't believe this ...

SP2 released

Office Project Server 2007 Sp2 has now been released.  see the details here - http://blogs.msdn.com/chrisfie/archive/2009/04/28/announcing-service-pack-2-sp2-for-microsoft-project-2007-and-microsoft-project-server-2007.aspx .  see teh webcast here http://blogs.msdn.com/brismith/archive/2009/04/28/project-server-2007-service-pack-2-sp2-is-now-available.aspx Blogged with the Flock Browser

Reporting from Project Server 2016 - multiple sites and userviews

Just a quickie... I've been interested in how MS have handled the "multiple PWA sites in a Content DB" thing since I read that this was their new approach.  Most of my reporting is via SSRS so i am reliant (still... in 2016) on DB queries rather than OData feeds (tsk) and this "querying a PWA DB with more than one PWA site in it is unsupported" quote was worrying me. So it looks like what is happening is this. When you create the first PWA site in a Content DB it hard-codes the SiteID into the _Userview view design elements.  This means that your first PWA Site is the default.  All the data for subsequent sites are still held in the tables against separate SiteID's but you cannot utilise the OOTB _Userview components (see below) SELECT        ProjectFields.... FROM            pjrep.MSP_TVF_EpmProject('FF19B767-CA6D-4C4C-B123-C0B5AE5354D6') AS MSP_EpmProject  LEFT OUTER JOIN         ...