The permissions granted to user 'mydomain\myAccount' are insufficient for performing this operation - rsAccessDenied


Just a short post re the above SQL Reporting Services 2008 R2 error when running in Integrated Mode.

I found that PWA Administrator users could run RS Reports without issue, but any Project Server users accessing the reports were greeted with rsAccessDenied - The permissions granted to user 'mydomain\myAccount' are insufficient for performing this operation
I checked my RDL details and confirmed that:

- Report published to ProjectBICenter\Reporting%20Services doclib
- DC published to ProjectBICenter\Data%20Connections%20for%20Performancepoint

So my users should have permissions as these libraries inherit from the BI Center.
After experimenting with these permissions for a little while, it turns out the SP permission required was "Contribute" permission.  Now that's a new one!

So, I've:
- Created a new SP group and granted Collaborate on the site/sublibraries
- allocated my ProjectReportAuthors and Readers groups (AD) to this SP group.

And it works...ta da!

Comments

Popular posts from this blog

Restoring PWA Site to another Web App in the same Farm

The scenario is this: SharePoint 2016 Farm with Project Server Two Web Apps Development UAT One PWA on Development Web App. I want to copy the PWA Site on Development web app to UAT to support a testing cycle. As far as I knew there were two options: 1) Content Database Restore and Attach Process would be backup your Dev Content Database, Restore to a new Content Database for QA, then mount the database on the appropriate web app and your off.... Problem:  Although you can do this with the -AssignNewDatabaseID switch in Powershell (to avoid two content db's having the same database id) the Site Collection (PWA) in the db still retains its SiteID which means there is a duplicate SiteID in the Configuration Database.  This stops the PWA site being created and alllocated correctly and becomes essentially orphaned. This method is only any good for MOVING not COPYING Back to the drawing board... 2) Backup-SPSite / Restore-SPSite I didn't believe this ...

SP2 released

Office Project Server 2007 Sp2 has now been released.  see the details here - http://blogs.msdn.com/chrisfie/archive/2009/04/28/announcing-service-pack-2-sp2-for-microsoft-project-2007-and-microsoft-project-server-2007.aspx .  see teh webcast here http://blogs.msdn.com/brismith/archive/2009/04/28/project-server-2007-service-pack-2-sp2-is-now-available.aspx Blogged with the Flock Browser

Reporting from Project Server 2016 - multiple sites and userviews

Just a quickie... I've been interested in how MS have handled the "multiple PWA sites in a Content DB" thing since I read that this was their new approach.  Most of my reporting is via SSRS so i am reliant (still... in 2016) on DB queries rather than OData feeds (tsk) and this "querying a PWA DB with more than one PWA site in it is unsupported" quote was worrying me. So it looks like what is happening is this. When you create the first PWA site in a Content DB it hard-codes the SiteID into the _Userview view design elements.  This means that your first PWA Site is the default.  All the data for subsequent sites are still held in the tables against separate SiteID's but you cannot utilise the OOTB _Userview components (see below) SELECT        ProjectFields.... FROM            pjrep.MSP_TVF_EpmProject('FF19B767-CA6D-4C4C-B123-C0B5AE5354D6') AS MSP_EpmProject  LEFT OUTER JOIN         ...