Skip to main content

Return of the data-geek. EPM OLAP Cube Custom Measures

I thought i'd put rogether a quick post on Cube customisation, as this is something that I am constantly asked about. Now I am not an MDX expert at all, but there are some useful results you get from some pretty simple MDX expressions.

Firstly, custom measures are done in the OLAP Cube Database Management section of the Project Web App Server Settings page.  Hightlight the cube you want to customise and then click Configure.

Once in this section you need to scroll down to the bottom and decide which cube you want to add the measure to in the OLAP database.  Generally in most scenarios, the Portfolio Analyser cube is the best target, depending on the data you wish to interrogate.  Once the cube is selected, click Insert.

S-Curves
OK, so you've got a decent OLAP report (in excel, PerformancePoint Services or the like) showing data by month, but you been asked for a nice S-curve report showing Baseline, Work and Actual Work on a cumulative curve.  As with all useful things, its short but complex query that is needed.

This example would give you a cumulative WORK calculation, specifically from the earliest date possible.
>  sum(periodstodate([time].[(all)]),[measures].[Work])

This example is a little more simple and would do the same but only over this year
>  sum(periodstodate([time].[Year]),[measures].[Work])

This example is the associated Actual Work S-Curve but allows for there to be NULL values where no actual work exists - in the future - rather than the S-Curve flatlining after the last reporting period.
> iif([actual work]=0,NULL,sum(periodstodate([time].[(all)]),[measures].[actual work]))

Capacity Heatmap (Remaining capacity percentage)
A nice simple one for Excel Services conditional formatting, calculating the % of capacity that is remaining based on the Work values.
> ([Capacity]-[work])/[capacity]


Filtering a measure based on a dimension member to derive custom cube measures

imagine the scenario.  On your report you want to put the following onto a stacked column chart
- Actual Work spent on Project Priority 1 projects
- Actual Work spent on Project Priority 2-4
- Resource Capacity (as a line)

note:  Your priority field is a flat Lookup Table that doesnt have this "P2-4" grouping built in

In this scenario to easily derive these values:
1 - Create a measure for Actual Work spent on P1 projects: 
ActWorkP1                   ([measures].[actual work],[Project Priority_Project].[Priority 1])
2 - Create a measure for Actual Work spent on "everything else" besides P1 Projects
ActWorkP2-4                [Actual Work]-[ActWorkP1]

This may seem like an edge case and you can of course use a pivot table to cross analyse and filter for these values, but what this DOES give you is an interesting OLAP based source for KPI's....

Next target:  I am currently looking at how I can derive a custom measure of the actual work done on one "Administrative" task across any given timesheet period....

More to follow!

Comments

Popular posts from this blog

Issues update on #projectserver2013 - Timesheets and Publishing

Reporting Publish ** updated with links to other related discussions, and a VBA macro ** the following issue has been noted on publish since June 13 CU was applied: ReportingProjectChangeMessageFailed (24006) - Object reference not set to an instance of an object.. Details: id='24006' name='ReportingProjectChangeMessageFailed' uid='4d869e56-f625-e311-bb41-005056b90052' QueueMessageBody='Project UID='e3f49977-b2bc-e211-8559-005056b90052'. PublishType='ProjectPublish'' Error='Object reference not set to an instance of an object.'. I have seen this noted previously on a similar issue: http://nearbaseline.com/blog/2013/06/ms-reporting-project-publish-jobs-failed-after-aprilcu/comment-page-1/#comment-14741 This is  caused by Baselined Milestones having NULL Baseline Cost values Original bug note with potential workaround is here: http://blogs.msdn.com/b/brismith/archive/2012/05/23/project-server-2007-reporting-project-pu...

#projectserver2013 VIEW FAILURE: The view failed to load. Press OK to reload this view with the default settings. Press cancel to select another view.

** UPDATE ** includes notes relating to secondary bug where Timesheet is created without Administrative tasks. Does this ring any bells? This has been bugging me for months, but finally I have a repro for this: Issue Summary:  When a task is deleted from a plan that is approved into a previous or current timesheet - even when there are no actuals on the task - you can no longer view the timesheet The following repro has been proven: - Setup system with Single Entry Mode, with enforced Status Approval before Timesheet Approval - Create resource as own timesheet manager - Create new project - Create two tasks in the same week, starting monday with 5 days duration:  1) Task to assign actuals, 2) Task to delete post submission - Assign Resource to tasks - publish project - as Timesheet User, go to the appropriate timesheet period for the tasks created - Assign actual work to one task (task 1), leaving task 2 with no actual work - Submit timesheet - as Project ...

Restoring PWA Site to another Web App in the same Farm

The scenario is this: SharePoint 2016 Farm with Project Server Two Web Apps Development UAT One PWA on Development Web App. I want to copy the PWA Site on Development web app to UAT to support a testing cycle. As far as I knew there were two options: 1) Content Database Restore and Attach Process would be backup your Dev Content Database, Restore to a new Content Database for QA, then mount the database on the appropriate web app and your off.... Problem:  Although you can do this with the -AssignNewDatabaseID switch in Powershell (to avoid two content db's having the same database id) the Site Collection (PWA) in the db still retains its SiteID which means there is a duplicate SiteID in the Configuration Database.  This stops the PWA site being created and alllocated correctly and becomes essentially orphaned. This method is only any good for MOVING not COPYING Back to the drawing board... 2) Backup-SPSite / Restore-SPSite I didn't believe this ...