Skip to main content

Using the RESUME field to reschedule incomplete work #projectserver

Since MS provided the ability to plan only using PWA, this has been a really useful feature for some users.  However there has always been a (certainly from my perspective) perceived issue, in that the ability to reschedule incomplete work into the future (a key component of the planning cycle) was only available in MS Project client.

The other day I was asked by a customer how they could get around this issue.  They use PWA extensively (cost reasons) for planning but were struggling with realising correct resource forecast data as they PM's were not able to re-forecast their remaining work schedule.

As we had recently patched the Project Server to 2013 SP1 + 0614CU I thought I would look at the STOP/RESUME fields in the Project views to see if these were editable, and surprise surprise they were.

The stop/resume fields are how MS Project handles task splits and the "update remaining work to restart after" component of rescheduling.  The Stop field will indicate the last day that progress was added to the task (either via % Complete or Timephased Actual Work edits/status updates) and by default the resume field will be the next day (or minute, in truth)

If you edit the resume field to a date in the future, then the task becomes split and the remaining work moves forward to restart from that date.

Don't ask me to explain multiple or manual splits.  I can't

Anyhoo... the repro

Firstly create a new project, with one task on it with 10d duration for simplicity of querying, and assign one resource to the assignment and publish the schedule


As the user assigned to the task, complete the first day of actual work and submit

As the Project Owner, approve the task.  Then go into Approval History and publish the assignment

Wait until it publishes

Then open the project in PWA for editing.

Set the Resume date to some time in the future, in this example 18th August
Note the finish date changes

Now query the assignmentbyday table and see the work move forward (ignore the nulls in my results, these have been replaced in my query to make it easier to discern between 0's and 8's!)


Notice that the planned work now has a gap between the 1d actuals assigned and the Resume date of 18 August

HURRAH!!!




Comments

Popular posts from this blog

#projectserver2013 VIEW FAILURE: The view failed to load. Press OK to reload this view with the default settings. Press cancel to select another view.

** UPDATE ** includes notes relating to secondary bug where Timesheet is created without Administrative tasks.

Does this ring any bells?

This has been bugging me for months, but finally I have a repro for this:

Issue Summary:  When a task is deleted from a plan that is approved into a previous or current timesheet - even when there are no actuals on the task - you can no longer view the timesheet

The following repro has been proven:
- Setup system with Single Entry Mode, with enforced Status Approval before Timesheet Approval
- Create resource as own timesheet manager
- Create new project
- Create two tasks in the same week, starting monday with 5 days duration:  1) Task to assign actuals, 2) Task to delete post submission
- Assign Resource to tasks
- publish project
- as Timesheet User, go to the appropriate timesheet period for the tasks created
- Assign actual work to one task (task 1), leaving task 2 with no actual work
- Submit timesheet
- as Project Status Manager, approve the time on task 1 …

What to do when your application server goes bang

What happens when someone kills your Application Server?
So imagine the scenario:
Three Server Solution - SQL - SharePoint 2010 and Project Server 2010 Application Server (Central Admin Host) - Wfe/ReportServer
We wake one bleary Monday morning to find that some numpty has killed the application server and the users are baying for blood.
Well surprisingly SharePoint handles this disaster recovery scenario particularly well.  Well.  Better than I thought it would to be honest.
Rough steps:
- quick SQL backup to be safe - Rebuild your application server - reinstall pre-reqs - reinstall SP, PS, SPFSP1, SPS+PSSP1, Cumulative Update and other stuff you usually put on there. - Run your configuration wizard to reattach to the Farm, and select Host CA Site
The last step was what I was VERY wary of.  Would the server simply reattach to the Farm, even when there is no CA server available?  
Bingo your back.... almost.... you are going to get errors a-gogo in your event log as things just aren't quite back…

Reporting from Project Server 2016 - multiple sites and userviews

Just a quickie...
I've been interested in how MS have handled the "multiple PWA sites in a Content DB" thing since I read that this was their new approach.  Most of my reporting is via SSRS so i am reliant (still... in 2016) on DB queries rather than OData feeds (tsk) and this "querying a PWA DB with more than one PWA site in it is unsupported" quote was worrying me.

So it looks like what is happening is this.

When you create the first PWA site in a Content DB it hard-codes the SiteID into the _Userview view design elements.  This means that your first PWA Site is the default.  All the data for subsequent sites are still held in the tables against separate SiteID's but you cannot utilise the OOTB _Userview components (see below)


SELECT        ProjectFields....
FROM            pjrep.MSP_TVF_EpmProject('FF19B767-CA6D-4C4C-B123-C0B5AE5354D6') AS MSP_EpmProject 
LEFT OUTER JOIN
                      pjrep.MSP_TVF_EpmInternalProjectHierarchies('FF19B767-CA6…