Project Server 2013 and manually entered baselines not saving to database

**Quick publish article.  Further tests follow** **Update:   Only appears to apply to on-premise installs.  Project Online is unaffected ** Issue:  When manually editing Baseline(0-10) timephased data via task usage in MS Project Client, data is not saved to database. Tested on:  SEPT 2015 PU (Server and Client) Prep: ------------------------------------------------------- Create a project with one task on it.   add a resource from pool and assign to the task at 100% Set Baseline (0) Publish plan Test:  Query DB and see timephased data populated correctly Issue 1 Repro ------------------------------------------------------- Edit Baseline Work values in Task Usage view Save and Publish Test:  Query DB and see timephased data is not changed Issue 2 Repro ------------------------------------------------------- Add Baseline 10 to task usage view Manually enter values into timephased cells for Baseline10 Save and Publish Test:  Query DB and see timephased d