Skip to main content

Project Server 2013 and manually entered baselines not saving to database

**Quick publish article.  Further tests follow**
**Update:  Only appears to apply to on-premise installs.  Project Online is unaffected**

Issue:  When manually editing Baseline(0-10) timephased data via task usage in MS Project Client, data is not saved to database.

Tested on:  SEPT 2015 PU (Server and Client)

Prep:
-------------------------------------------------------
Create a project with one task on it.  
add a resource from pool and assign to the task at 100%
Set Baseline (0)
Publish plan

Test:  Query DB and see timephased data populated correctly



Issue 1 Repro
-------------------------------------------------------
Edit Baseline Work values in Task Usage view
Save and Publish

Test:  Query DB and see timephased data is not changed



Issue 2 Repro
-------------------------------------------------------
Add Baseline 10 to task usage view
Manually enter values into timephased cells for Baseline10
Save and Publish

Test:  Query DB and see timephased data is not changed




Issue 3 Repro
-------------------------------------------------------
Close MSP file
Remove from Cache
open file

Test:  See that previously edited values in Baseline 0 and Baseline 10 are missing.  Original Baseline data (set using Set Baseline) is displayed


Summary findings
-------------------------------------------------------
It looks like manually edited baseline values are not moving from Cache to Database on Save and therefore the reporting db isnt being updated.




SQL Script for test:
-------------------------------------------------------

--Baseline 0
SELECT         b.TimeByDay, b.AssignmentBaselineWork
FROM (SELECT * FROM MSP_EpmProject WHERE ProjectName = 't1bltest') P
INNER JOIN MSP_EpmAssignment A 
         on           p.projectuid = a.projectuid
INNER JOIN MSP_EpmAssignmentBaselineByDay B 
         on           a.AssignmentUID = b.AssignmentUID
WHERE          b.BaselineNumber = 0

--Baseline 10:
SELECT         b.TimeByDay, b.AssignmentBaselineWork
FROM (SELECT * FROM MSP_EpmProject WHERE ProjectName = 't1bltest') P
INNER JOIN MSP_EpmAssignment A 
         on           p.projectuid = a.projectuid
INNER JOIN MSP_EpmAssignmentBaselineByDay B 
         on           a.AssignmentUID = b.AssignmentUID
WHERE          b.BaselineNumber = 10

Comments

  1. I think this is an issue I've run into before. You need to change the scalar value, i.e. the total work or some field for the baseline in question. That's what triggers MPP to see that the baseline has changed and will then cause it to save the timephased values. See if that works.... (http://azlav.umtblog.com/2012/01/10/capturing-custom-timescaled-data-in-project-professional-part-i/)

    ReplyDelete

Post a Comment

Popular posts from this blog

#projectserver2013 VIEW FAILURE: The view failed to load. Press OK to reload this view with the default settings. Press cancel to select another view.

** UPDATE ** includes notes relating to secondary bug where Timesheet is created without Administrative tasks.

Does this ring any bells?

This has been bugging me for months, but finally I have a repro for this:

Issue Summary:  When a task is deleted from a plan that is approved into a previous or current timesheet - even when there are no actuals on the task - you can no longer view the timesheet

The following repro has been proven:
- Setup system with Single Entry Mode, with enforced Status Approval before Timesheet Approval
- Create resource as own timesheet manager
- Create new project
- Create two tasks in the same week, starting monday with 5 days duration:  1) Task to assign actuals, 2) Task to delete post submission
- Assign Resource to tasks
- publish project
- as Timesheet User, go to the appropriate timesheet period for the tasks created
- Assign actual work to one task (task 1), leaving task 2 with no actual work
- Submit timesheet
- as Project Status Manager, approve the time on task 1 …

What to do when your application server goes bang

What happens when someone kills your Application Server?
So imagine the scenario:
Three Server Solution - SQL - SharePoint 2010 and Project Server 2010 Application Server (Central Admin Host) - Wfe/ReportServer
We wake one bleary Monday morning to find that some numpty has killed the application server and the users are baying for blood.
Well surprisingly SharePoint handles this disaster recovery scenario particularly well.  Well.  Better than I thought it would to be honest.
Rough steps:
- quick SQL backup to be safe - Rebuild your application server - reinstall pre-reqs - reinstall SP, PS, SPFSP1, SPS+PSSP1, Cumulative Update and other stuff you usually put on there. - Run your configuration wizard to reattach to the Farm, and select Host CA Site
The last step was what I was VERY wary of.  Would the server simply reattach to the Farm, even when there is no CA server available?  
Bingo your back.... almost.... you are going to get errors a-gogo in your event log as things just aren't quite back…

Reporting from Project Server 2016 - multiple sites and userviews

Just a quickie...
I've been interested in how MS have handled the "multiple PWA sites in a Content DB" thing since I read that this was their new approach.  Most of my reporting is via SSRS so i am reliant (still... in 2016) on DB queries rather than OData feeds (tsk) and this "querying a PWA DB with more than one PWA site in it is unsupported" quote was worrying me.

So it looks like what is happening is this.

When you create the first PWA site in a Content DB it hard-codes the SiteID into the _Userview view design elements.  This means that your first PWA Site is the default.  All the data for subsequent sites are still held in the tables against separate SiteID's but you cannot utilise the OOTB _Userview components (see below)


SELECT        ProjectFields....
FROM            pjrep.MSP_TVF_EpmProject('FF19B767-CA6D-4C4C-B123-C0B5AE5354D6') AS MSP_EpmProject 
LEFT OUTER JOIN
                      pjrep.MSP_TVF_EpmInternalProjectHierarchies('FF19B767-CA6…